Every public-private partnership is a bargain over who carries which risk, and the price follows the allocation: a party that cannot manage a risk will either charge for it or fail under it. This worksheet lists the risks common to toll-road and infrastructure concessions, lets you assign each one to the public partner, the private partner or both, and shows how much of the total risk each side ends up holding.
Worksheet
For each risk, choose who carries it, and rate its likelihood and impact from 1 (lowest) to 5 (highest). The starting ratings are illustrative examples for a generic toll road. Replace them with your own assessment of your project.
Results
Exposure by risk group
How the scoring works
- Risk score is likelihood multiplied by impact, from 1 to 25. Scores of 15 or more are labelled High, 8 to 14 Medium, and 7 or less Low.
- Allocation sets the public share of each risk: Public 100% is 100% public, Mostly public is 75% public, Shared is 50% each, Mostly private is 25% public, and Private 100% is 0% public.
- Exposure is the risk score multiplied by each partner's share. Adding these across all risks gives each partner's total exposure and its percentage of the total.
- Commonly used allocation shows where the risk usually sits in road concessions, following the principle that a risk belongs with the party best able to control or insure it. It is a reference point, not a rule. A project can differ from it for good reasons. A risk is listed as different when your allocation is two or more steps away from it on the five-step scale.
Worked example
With the starting ratings and every risk set to its commonly used allocation, the 14 risks add up to a total score of 162. The public partner holds about 83.8 of that (51.7%) and the private partner about 78.3 (48.3%). Four risks score 15 or more: land acquisition and cost overrun, each held by one side, and traffic volume and exchange-rate movement, each shared equally.
Now move exchange-rate movement from Shared to Private 100%. The public share falls to about 73.8 (45.5%) and one risk now differs from the commonly used pattern. Also move traffic volume to Private 100% and the public share falls to about 66.3 (40.9%), with two risks differing. The scores did not change. Only the allocation moved, so the private partner now carries three of the four high-scoring risks and may price or finance accordingly. Figures are illustrative and not a view on any real project.
Assumptions and limits
- The list covers 14 common risks. Add any project-specific risks to your own notes, such as security, community relations or the handback standard.
- Scores are judgement-based. Two reviewers may rate the same risk differently, so agree ratings before comparing allocations.
- Likelihood and impact are treated as equally weighted and the scale is not a probability or a naira amount.
- Contracts often share a risk through formulas, caps, floors or compensation events, which a five-step allocation cannot capture.
Use the results to prepare discussion, not to replace legal or financial advice. See also the Concession Break-Even Test and the Foreign Loan Cost Calculator.
Common questions
Why does the same risk sometimes appear on both sides?
Some risks are hard to control for either partner, such as traffic volume or a flood. Sharing them can lower the total cost of the project, because neither side has to price the full risk alone.
Is a more even split always better?
Not necessarily. An even split of total exposure says little if a partner carries risks it cannot manage. Look at which partner holds the High-scoring risks and whether it can influence them.
Who should complete the worksheet?
Ideally both sides, separately, then compare the results. Gaps between the two versions show where negotiation will be needed.